If you just received a notice that your neighborhood’s power lines are going underground, you probably have a few immediate questions: Will I need a new electrical panel? Is someone going to dig up my yard? And what am I actually on the hook to pay for?
First, take a deep breath. Receiving an undergrounding notice does not automatically mean you have to replace your main electrical panel. While some homes will need equipment adjustments before connecting to the new underground lines, others can simply use their existing setups. As San Diego Gas & Electric (SDG&E) points out, every property gets its own custom construction plan, and panel replacements are only required in certain situations.
The best place to start is with the notice in your mailbox. Understanding exactly what the project covers and what you’ll be responsible for can prevent unnecessary work and make the whole process less stressful.
What Is an Underground Electrical Service Conversion?
Simply put, an underground service conversion changes how electricity travels to your home, shifting the incoming lines from overhead poles to pipes hidden safely below ground.
In our area, the City of San Diego’s Utilities Undergrounding Program works alongside SDG&E to manage these neighborhood transformations. The work typically involves digging trenches, laying conduit (protective piping), running new cables, and hooking homes up to the new system.
Note: SDG&E also runs a separate Strategic Undergrounding Program focused specifically on high-risk wildfire areas. Because the rules and scope can vary between these programs, always refer to the specific paperwork sent to your address.
Will You Actually Need an Electrical Panel Upgrade?
Maybe, but there’s no need to jump the gun. Receiving a notice isn’t a reason to go out and buy a brand-new panel right away.
If someone tells you that your panel needs to be replaced, pause and ask for specifics. Before paying for anything, make sure you understand exactly which type of work is being requested. There are three main types of work you’ll likely encounter:
- Required Work: Adjustments mandatory for connecting your home to the new underground lines.
- Code Corrections: Fixes needed to bring older, existing equipment up to current safety standards.
- Optional Upgrades: Extra capacity improvements you choose to make while an electrician is already on-site.
If it turns out you do need an electrical panel upgrade, or if you decide to add capacity for the future, you don’t have to carry the full cost alone. Many homeowners qualify for local utility rebates, state energy programs, or federal tax credits through the Inflation Reduction Act.
Sorting through rebate requirements can be confusing, but you don’t have to figure it out by yourself. At Point Loma Electric, Plumbing, Heating & Air, we help you identify available incentives to help you maximize your savings on any required or optional electrical panel upgrades.
Who Handles the Work (and Who Pays for What)?
A typical undergrounding project involves a few different players: the City, SDG&E, city contractors, and sometimes an electrician you hire yourself. Here is how the roles usually break down:
City or Neighborhood Project
For City-managed projects, the City handles the big-picture items: planning, neighborhood permits, scheduling, and public updates. Your project notices and the City’s online portal are your best resources for tracking timeline updates.
SDG&E
SDG&E decides where and how the new underground lines connect to your home. Their rules strictly require written confirmation of your approved “service-delivery point” (the official connection spot). Pro tip: Never assume your connection point will be the same as your neighbor’s or rely on a verbal comment from a crew member; always get it in writing!
The Homeowner
As the homeowner, your main job is returning permission forms, granting property access, and handling any required safety corrections on your home’s side of the equipment.
According to City guidelines, if your electric meter panel is outdated or doesn’t meet minimum safety codes, fixing those pre-existing issues is the homeowner’s responsibility. Similarly, if you ask for custom (optional) upgrades outside the project scope, those costs fall to you.
Your Licensed Electrician
If your property does require work that isn’t covered by the City or SDG&E, you’ll need to hire an electrician. Always share your project notice, written utility requirements, and any correction notices with them before asking for a quote.
Make sure your electrician provides a detailed written proposal outlining what work is included, who pulls the permits, and how they will coordinate directly with SDG&E.
Understanding Your Meter, Main Panel, and Trench Route
These three terms get thrown around a lot during undergrounding projects. Here is a quick breakdown of what they actually mean for your home:
Meter & Service Equipment
The meter measures your power usage, and the surrounding box connects incoming utility lines to your home. Any changes here must match SDG&E’s exact specifications.
Main Electrical Panel
This is the breaker box that distributes electricity throughout your home. Depending on your setup, it might be combined with your meter or mounted separately. Always verify if panel work is a strict project requirement or just a recommendation.
The Trench Route
This is the path the crew will dig across your yard to bury the lines. The City program covers trenching directly to your home. Before work starts, ask where the path will go, how it affects your yard or driveway, and who handles putting the landscaping back in place.
What to Do When You Receive an Undergrounding Notice
When that letter arrives, don’t rush to book an electrician right away. Instead, start by organizing your paperwork.
Grab a folder and keep these key items together:
- Your official project notice and project number
- Any Permission to Enter or permit forms
- Any correction notices you receive
- Contact info for your utility or project representative
- Any property site maps provided
Once your paperwork is organized, reach out to your assigned City/SDG&E project representative (and your electrician, if private work is needed) with these 6 questions:
- Where is my approved connection point? (Ask SDG&E or the City for written confirmation.)
- What work is covered by the public project?
- Does my home need a safety correction?
- What needs to happen before connection day? (Ask the project planner to clarify access, trenching paths, and prep work.)
- Is a proposed panel upgrade required or optional? (Ask your electrician to separate connection mandates from optional improvements.)
- Who is pulling the permits? (Confirm whether your electrician or the project team handles city inspections.)
A Quick Note on Safety During Construction
While construction is happening around your home, safety comes first:
- Never remove panel covers, open meter enclosures, or dig along the proposed route yourself.
- Leave all excavation, utility locating, and heavy wiring to qualified professionals.
- In an emergency: If you ever see smoke, fire, or active electrical arcing, stay clear and call 911 immediately.
Have Questions About Your Home’s Electrical Panel?
If you’ve received an undergrounding notice and aren’t sure what your home needs, Point Loma Electric, Plumbing, Heating & Air is here to help.
Give us a call today at (619) 224-0672. Just have your project notice or correction letter handy, and our friendly team will help you take care of the rest.
Undergrounding – Frequently Asked Questions
Does undergrounding mean my main panel MUST be replaced?
No. While some properties require an equipment tweak or panel swap, undergrounding does not automatically require a brand-new panel for every home. Always verify your property’s specific requirements before signing off on work.
Who decides where the new underground lines connect?
SDG&E determines the official service-delivery point. Be sure to get this location confirmed in writing from the project planner before hiring an electrician to move or replace any equipment.
Is the trench digging on my property covered?
Yes, the City’s undergrounding program includes trenching across private property to reach individual homes. Double-check your project documents to confirm the exact route and landscape restoration details.
What should I do if I get a correction notice?
Don’t panic! Read the notice carefully and call the listed project representative with any questions. A correction notice usually just points out an access issue or a minor code update. It rarely means you need a full panel replacement.